Why is a Work Center assigned to a Cost Center?
Why is a Work Center assigned to a Cost Center?
A . For assignment to find suitable people
B. For costing to use activity types
C. For scheduling to determine transportation time and queue time
D. For capacity to use shift sequences
Answer: B