Which option should you enable on the ticket template to avoid creation of multiple tickets?

A maintenance plan is created with the condition "Every 5 weeks". Based on this condition, a ticket is created on March 1, but ticket processing is delayed.

Which option should you enable on the ticket template to avoid creation of multiple tickets?
A . Consider ticket resolved on date
B. Consider contract status
C. Consider maintenance plan condition
D. Consider delay

Answer: A