Which of the following must you do before the system can check the minimum remaining shelf life during the goods receipt for a purchase order (PO)?
CORRECT TEXT
Which of the following must you do before the system can check the minimum remaining shelf life during the goods receipt for a purchase order (PO)?
Note: There are 2 correct Answers to this question.
Enter the earliest acceptable expiration date in the PO item.
B. Activate the shelf life expiration date (SLED) check in customizing.
C. Enter the remaining shelf life in the material master record
D. Activate batch management for the material.
Answer: B, C