Which of the following statements are correct about the Sprint Goal? (choose all that apply)
Which of the following statements are correct about the Sprint Goal? (choose all that apply)
A . The Sprint Goal provides the Developers with a target, focus, and overarching direction for the Sprint
B. The Developers commits to the Sprint Goal and forecasts the Sprint Backlog
C. The Sprint Goal is crafted by the Product Owner in collaboration with the stakeholder
D. The Sprint Goal is the outcome of the Product Backlog Refinement meeting and it helps the team with effective Sprint Planning
E. The Scrum Team forecasts the Sprint Goal and commits the Sprint Backlog.
F. The Sprint Goal is the glue that binds individuals into a team by giving them a shared purpose.
Answer: A,B,F
Explanation:
Scrum Guide:
Commitment: Sprint Goal
The Sprint Goal is the single objective for the Sprint. Although the Sprint Goal is a commitment by the Developers, it provides flexibility in terms of the exact work needed to achieve it. The Sprint Goal also creates coherence and focus, encouraging the Scrum Team to work together rather than on separate initiatives.
The Sprint Goal is created during the Sprint Planning event and then added to the Sprint Backlog. As the Developers work during the Sprint, they keep the Sprint Goal in mind. If the work turns out to be different than they expected, they collaborate with the Product Owner to negotiate the scope of the Sprint Backlog within the Sprint without affecting the Sprint Goal.