After a risk assessment is performed, a particular risk is considered to have the potential of costing the organization 1.2 Million USD.

After a risk assessment is performed, a particular risk is considered to have the potential of costing the organization 1.2 Million USD.

This is an example of
A . Risk Tolerance
B. Qualitative risk analysis
C. Risk Appetite
D. Quantitative risk analysis

Answer: D

Latest 512-50 Dumps Valid Version with 404 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments