True or False: Work Item Age is a leading indicator for the length of the Scrum Team’s feedback loop for that (in progress) item.
True or False: Work Item Age is a leading indicator for the length of the Scrum Team’s feedback loop for that (in progress) item.
A . True
B. False
Answer: A
Explanation:
If an item is aging quite a bit it is certainly an indication that its Cycle Time will be high. Cycle Time throughout the Scrum Team’s definition of Workflow can also be considered the length of the team’s feedback loop.
Latest PSK-I Dumps Valid Version with 350 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments