What are the first two areas that should be identified in value stream mapping? (Choose two.)

What are the first two areas that should be identified in value stream mapping? (Choose two.)
A . The bottleneck
B. The people who supervise the work
C. Process time, lead time, and percent complete and accurate
D. The steps
E. The people who do the work

Answer: D,E

Explanation:

https://www.scaledagileframework.com/operational-value-streams/

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments