What is the lead time for a particular step in a value stream?

What is the lead time for a particular step in a value stream?
A . Time from when the work is ready from the previous step to work completion.
B. Waiting time at a particular step
C. Process time at a particular step
D. Time taken to complete a task at a particular step

Answer: A

Explanation:

Value stream mapping metrics include following: