Which statements about the Product Backlog are correct?

Which statements about the Product Backlog are correct?
A . The Product Backlog contains only items that are completely refined.
B. In the Product Backlog, Items at the top are usually smaller than on the bottom.
C. The Product Backlog is never baselined.
D. The Product Owner is accountable for the Product Backlog.

Answer: B,C,D

Explanation:

The Product Backlog is never refined as it constantly evolves. In Scrum, to "baseline" something means to fixing something – the Product Backlog will never be fixed. Items at the bottom are usually unclear and not well refined. Therefore they are usually bigger.