Which two items should a consultant include in the scheduling policy to meet this requirement?

universal container UC wants to create a new scheduling policy that takes into account the technician assigned to customers account and then considers a resource from the customer group of preferred technician UC also wants to consider only technician with 50 miles of schedule work

Which two items should a consultant include in the scheduling policy to meet this requirement?
A . Minimize travel service objectives and resources priority services objectives
B. Maximize travel from home and working territories
C. Required resources and maximum travel from home
D. Minimize travel service objective and preferred resource services objectives

Answer: B,D