What is the purpose of the work center assigned to the reference object in a work order? There are 2 correct answers to this question.

What is the purpose of the work center assigned to the reference object in a work order? There are 2 correct answers to this question.
A . It is needed to post the goods issue.
B. It is needed to settle the order.
C. It is needed to calculate the planned costs.
D. It is needed to schedule the operations.

Answer: C,D