Which apps can be accessed from the KPI cards in the advanced version of Fiori app Resource Management for Projects? Note: There are 2 correct answers to this question.

Which apps can be accessed from the KPI cards in the advanced version of Fiori app Resource Management for Projects? Note: There are 2 correct answers to this question.
A . Manage Project Assignments
B. Manage Project Staffing
C. Manage Resource Utilization
D. Manage Resource Requests

Answer: B,C

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments