For which objects can you perform budget availability control? (Choose two.)
For which objects can you perform budget availability control? (Choose two.)
A . Internal Order
B . Profit Center
C . Project
D . Cost Center
Answer: A,D
Explanation:
Reference: https://blogs.sap.com/2019/12/24/budget-availability-control-for-cost-centers-in-sap-s-4hana-1909/
Latest C_S4CFI_2208 Dumps Valid Version with 79 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments